Notable Moments – Security Applications & Technologies

Administrative

Completion of 2023 Security Master Plan. Digital copy published to SAT website, print versions available for distribution

Conducted security assessments of building compliance level in relation to the campus minimum security standards. Provided cost estimates by building for incorporation into Facilities FCAP and IPL tools

 Repair and new project parts inventories moved from VRB to Materials Warehouse

2022-23 Maintenance Agreements billing completed & paid in August, 2022. 58 agreements, $1,343,723

SAT hired two SHRA employees, Dylan Quick (IT Ops Technician) and Eric Fox (Security Technician)

Recruitment of contract positions including developers (Jeremy Gibson, Ravi Jujjuri, Zane Helton and Ryan Semmler), tech support analyst (Kevin Kwon) and various student programmer positions

Don Ellis building renovation design nearing final SCO approval

Application Support

Completed replacement/upgrade of 685 access control circuit boards

Comprehensive cleanup of outdated Genetec camera system naming convention and programming naming conventions for a more standardized and streamlined camera view names. (3,100+ cameras)

Comprehensive renaming of doors across Ccure System and added field to identify department owner to assist with WOS data (3,800+ access control points)

Major access control Clearance Clean Up initiative has been completed and applied to Ccure to assist with Security Liaisons that are using the new SAT Liaison Clearance tool

Updated campus door access system (CCure 9000) to latest version (3.09)

Updated campus-wide camera firmware for 3100+ IP cameras

Eliminated PCI CCure system with decommissioning of the Admin III data center

Updated campus alarm system receiving software (Compass / 7810 PC to accommodate the newest Honeywell panels for IDS (intrusion detection system)

Team leaders on the project management unit attended ASIS Security Conference to learn more about new trends and technologies in the security industry

Field Operations

15,855 SAT Service Tickets July 1, 2022 – June 12, 2023

Replaced/updated IP intercoms in 27 Security Stanchions

Technician training on rebuilding electronic hardware in response to supply chain issues allowed us to facilitate additional projects where hardware supply wasn’t available

Technicians training on the CCURE 9000 access control platform

Technicians trained and certified on fall protection, aerial lifts, scissor lifts and metal detectors

IT Operations

Monthly and quarterly software updates, builds, patches of infrastructure software

Operating System upgrades to latest supported O/S for all SAT servers and desktops

SAT Firewall rules clean-up

Internal hardware refresh for all staff who had legacy hardware

Implementation of Kubernetes Clusters for Development, Test and Prod environments

Implemented Linux O/S patching and reboot automation using CLS Puppet Infrastructure

Completed Industrial Switch Upgrade to Extreme Switches started prior year

IT Development

Complete rewrite of the web and service layer for SAT development assets

Adoption of Python based Microservice architecture for development of tools

Implementation of devops based CI/CD build automation using NCSU based GitHub actions

Creation and release of several new software tools in support of university needs including clearance assignment and user lookup tools which allows security liaisons to self-assign clearances to individuals for their respective areas of responsibility

Migrate all SAT developed applications to container based deployments in above Kubernetes Clusters
Completed Partial Migration of the Clearance Management tool to the C-Cure API

Project Design/Delivery

84 Projects – 84 Completed
79 Projects in WIP/New/Pending

FY2022-23 Project Revenue:

  • Project revenue $ 682,268.11
  • Project value $1,238,370.97

Project Breakdown

Project value $50K & greater
Greek Village Phase IV (ongoing) $356,628.64
JHL – FL02 Turnstile Array replace 4 single lane turnstiles: $156,338.75
Coliseum Deck – Camera Update: $74,918.37
EB3 – Camera Installation: $ 59,362.37

Project value range
Project values under $5,000 (47)
Project values $5,000 – $9,999 (17)
Project values $10,000 – $49,999 (17)
Project values $50K and over (4)

SAT In-House Projects Completed (77)
Completed projects include the Coliseum Deck
Camera Update and the Point Chancellors Residence Cart Path Cameras
Total project value (77) Projects: $497,144.53

Externally contracted projects (8)
Projects completed (8) includes JHL – FL02 Turnstile Array
Total project value (8) projects: $741,226.44

New people

SAT hired two SHRA employees: Dylan Quick (IT Ops Technician) and Eric Fox (Security Technician)

Awards, Certifications, Trainings, Significant Accomplishments

Manny Guzman – Master’s Certificate in Project Management – The Lewis Institute

Wallace Frist – Data Center Virtualization 2023 – VMWarre Learning

Will Butler – NC State 10 year Service Award

Will Butler – ITILv4 Foundations Training

Chris Vogler – Y12 National Security Complex Alarm Response Training Class – DOE

Chris Vogler – CCure 9000 Systems installer and maintainer – Johnson Controls

Eric Fox – CCure 9000 Systems installer and maintainer – Johnson Controls

John Ray – CCure 9000 Systems installer and maintainer – Johnson Controls

Dylan Quick- CCure 9000 Systems installer and maintainer – Johnson Controls

Kevin Kwon – CCure 9000 Systems installer and maintainer – Johnson Controls

Andrew Atterbury – CCure 9000 Systems installer and maintainer – Johnson Controls

Shawn Taylor – CCure 9000 Systems installer and maintainer – Johnson Controls

Wallace Frist – CCure 9000 Systems installer and maintainer – Johnson Controls